• Construction will continue to progress in the previously started areas around the hospital as highlighted below. Construction hours will continue to be Monday Saturday, 8 a.m. 5 p.m.
  • Completing installation of first floor concrete slab and starting installation of structural steel at the new hospital.
  • Continuing installation of concrete walls at the energy center.
  • Completing excavation of soil and installing underground storm water tanks.
    Continuing installation of storm drain along Lincoln Boulevard.