- Construction will continue to progress in the previously started areas around the hospital as highlighted below. Construction hours will continue to be Monday Saturday, 8 a.m. 5 p.m.
- Completing installation of first floor concrete slab and starting installation of structural steel at the new hospital.
- Continuing installation of concrete walls at the energy center.
- Completing excavation of soil and installing underground storm water tanks.
Continuing installation of storm drain along Lincoln Boulevard.